ECOWAS sets June 2027 launch for Praia - Dakar container service

ECOWAS ministers in Praia on 12-13 November 2026 agreed a roadmap to start a regular Praia - Dakar container liner service by June 2027 and to set up a Project Delivery Unit by December 2026.

ECOWAS sets June 2027 launch for Praia - Dakar container service
Participants at the ECOWAS meeting in Praia, Cabo Verde, on 12-13 November 2026 where plans for the Praia - Dakar container liner service were advanced. ECOWAS Commission

ECOWAS convened a meeting in Praia, Cabo Verde, on 12 to 13 November 2026 and agreed a roadmap to start a regular container liner service between Praia and Dakar by June 2027. ECOWAS says the link could improve maritime transport efficiency, strengthen regional value chains, support island economies and expand opportunities for small and medium-sized enterprises that trade across the region (see the ECOWAS press release and consolidated roadmap).

The two-day meeting followed a Council of Ministers directive from June 2026 in Freetown and brought together senior officials from member states, port authorities, maritime operators, regional development institutions and international financial partners (ECOWAS meeting page).

Delegates agreed a phased approach: the route will open first as a container liner service and a combined roll-on/roll-off passenger service (RoPax) will be introduced after two years. The meeting recommended creating a joint-venture company made up of existing operators from Cabo Verde, The Gambia, Guinea, Guinea-Bissau and Senegal, with gradual expansion to other coastal states.

To prepare for regular sailings, member-state authorities were asked to carry out coordinated, costed upgrades to port infrastructure and equipment. Practical issues raised included port readiness, vessel deployment options, cargo consolidation strategies, customs and border facilitation, digitalisation of maritime processes and compliance with safety and environmental standards.

Delegates at the ECOWAS meeting in Praia, Cabo Verde, 12-13 November 2026. ECOWAS Commission / ECOWAS

The meeting set a governance timetable: a dedicated Project Delivery Unit (PDU) must be established by the end of December 2026 to oversee all modalities and coordination mechanisms to ensure deployment of the container liner service by June 2027.

On financing, delegates reviewed operational and financing models and financial partners at the meeting reaffirmed their support. Earlier workshops in 2025 sought to define mixed financing mechanisms, such as public-private partnerships and regional funds, ahead of launch.

ECOWAS documents show end-2026 expectations were contingent on completing operational, infrastructure, governance and technical preconditions; the Praia meeting made those preconditions explicit with the PDU deadline (see the ECOWAS press release and consolidated roadmap).

According to ECOWAS records of a June 2025 workshop in Dakar, Chris Appiah, director of transport at the ECOWAS Commission, said the link would connect Cabo Verde to other West African states. ECOWAS records also quote Becaye Diop, director general of the Senegalese Maritime Affairs Agency, describing the project as strategically important for Senegal and Cabo Verde (ECOWAS meeting page).

ECOWAS's consolidated roadmap lists the next steps as finalising operational protocols, confirming vessel arrangements, establishing a cargo booking and information system, and keeping close coordination among ECOWAS, member states and financial partners. The project now needs the PDU and the finance models to show it can operate at scale.

Source: ECOWAS Commission